Open and view Gantt charts in our new frontend
July 2024
In the new frontend, LUY's masterplan diagram has been renamed to "Gantt Chart" to better reflect its purpose and functionality, similar to a classic Gantt chart.
Please be aware that this diagram is only renamed in the new frontend. Thereby we ensure compatibility throughout the “legacy” frontend.
The Gantt chart visualizes date intervals as bars, allowing you to display and compare intervals in a calendar view. You can display dates and date ranges for up to three related building block types as levels, with options for filtering, coloring, and adding attributes or relations as additional columns.
For our new frontend we’ve added some improvements like the ability to also use dark mode to view diagrams.

A full description of this diagram type can be found here: Gantt chart (former masterplan diagram).
For this version, the Gantt chart is in read only mode. You are able to open and view reports but can’t edit them yet.
Open diagram
Gantt chart reports can be opened either via the open diagram overlay or the reports page.

Open diagram overlay
The overlay shows a table of all Gantt chart reports available to you. These are either your own reports or reports which have been shared with you by other users.
In the dialogue you can see additional information like the author of the report as well as the last modified timestamp for each report.
If there is a long list of reports, use the filter option to search for specific reports by name.
There are two ways to open this overlay list:
Click on the Gantt chart tile in diagrams.
When a Gantt chart report is already open, by clicking on the Gantt chart text in the breadcrumb
All reports page
It is also possible to open a Gantt chart report via the reports page: Just click on the name of the report to open it.
Tip: The reports page allows you to filter not only by name but also by all other attributes of a report. E.g., it is possible to show GC-reports by filtering for “Gantt chart” or only show reports with certain tags by filtering for the tag name.
Navigate diagram
By clicking and holding your left mouse button you can move the diagram content.
Clicking CTRL while scrolling will zoom in and zoom out.
Limitations
Be aware that for this first iteration our new frontend does not yet support every feature known to you in our previous LUY solution. These features will follow shortly.
It’s not possible to edit a Gantt chart.
High contrast mode isn’t supported completely.
Some filters configurations aren’t yet support (e.g., filters for the version attribute).